Cost Breakdown & Payment Terms

เฅญเฅซ เคฒเคพเค–เคฎเฅˆ เค˜เคฐ เคคเคฏเคพเคฐ

Some Design of Houses Costing 75 Lakhs

๐Ÿ—๏ธ Construction Timeline (5 Months)

We are committed to completing your home within 5 months following this systematic work plan:

๐Ÿ“… Month 1: Substructure Works

  • Completion of foundation work up to the plinth beam level.

๐Ÿ“… Month 2: First Floor and Water Tank

  • Casting of the first-floor slab.

  • Construction of the underground water tank.

๐Ÿ“… Month 3: Upper Floors and Sanitary Tanks

  • Casting of the second and third-floor slabs.

  • Construction of the septic tank and soak pit.

๐Ÿ“… Month 4: Plaster, Wiring, and Plumbing

  • Full plastering work.

  • Completion of electrical wiring and plumbing installations.

๐Ÿ“… Month 5: Final Finishes

  • Installation of lights, sanitary fixtures, doors, and windows.

  • Final touches and handover preparation.

๐Ÿก Payment Timeline for Your Dream Home (Rs. 75,00,000)

๐Ÿ›‘ Step 1: No Advance Payment

๐Ÿ‘‰ After signing the contract, we start construction up to the lower tie beam at our own cost โ€” no advance needed!

โœ๏ธ Step 2: First Installment

Rs. 18,75,000 (25%)
๐Ÿ”น After completing the lower tie beam, we collect the first installment.

๐Ÿงฑ Step 3: Second Installment

Rs. 9,37,500 (12.5%)
๐Ÿ”น After finishing the plinth beam construction.

๐Ÿ—๏ธ Step 4: Third Installment

Rs. 9,37,500 (12.5%)
๐Ÿ”น After casting the first roof slab.

๐Ÿ  Step 5: Fourth Installment

Rs. 9,37,500 (12.5%)
๐Ÿ”น After casting the second roof slab.

๐Ÿข Step 6: Fifth Installment

Rs. 9,37,500 (12.5%)
๐Ÿ”น After casting the third roof slab.

๐Ÿงฑโœจ Step 7: Sixth Installment

Rs. 9,37,500 (12.5%)
๐Ÿ”น After all brick walls are completed and plastering is finished.

๐ŸŽ‰ Step 8: Final Installment

Remaining Balance
๐Ÿ”น Pay the final amount after full project handover.

Step-by- Step Construction Animated